CURRENT STATUS
downtown Muskegon, Michigan |
|
|
| |
|
|
|
|
|
|
|
| |
|
 |
|
|
Current Status:
-
Blue weather
proofing is going up and should be complete the week of May
25th. This includes extra blocking for stone attachment.
-
About half
the brick is up and washed. The rest will be up in about 2
weeks.
-
Most of the
second floor ductwork is installed. We are waiting for ceiling
tiles and the building becoming secure before finishing.
-
Plumbing has
been roughed in.
-
Electrical is
well along. Permanent power to the site is scheduled for May
29th.
-
95% of the
metal studs are installed.
-
The skylight
has arrived and will be installed the week of May 25th. All
parts are on the roof.
-
Window
installation starts the week of June 1st.
-
A landscape
contractor has been chosen.
-
We are
looking to finish the building in July 2008.
|
|
|
| |
|
|
|
|
|
|
|
| |
|
|
|
|
| |
|