POWER GENERATION AND UTILITY        
               
   

    CMS Energy BC Cobb Plant Ash Conditioning Pug Mill

This existing 2 story building, with basement, was renovated and converted from a mercantile use to use as a hospice and central offices.   Space includes a 9 bed hospice suite, clinical offices and exam rooms, administrative offices, and a leasable office suite on the second floor.  Also included in the project were a garden court, new walks and parking, and complete systems upgrade.
   
Project Cost   ..................................................................................................

$600,000

   
   
   

    DTE Energy Trenton Channel Power Plant Coal Crusher

This project consisted of engineering for a new coal crusher including all necessary building modifications, structural support, support platforms, and maintenance rigging.  Scope also included mechanical engineering for equipment installation, utility re-routing, erection specification, and functional system description.
   
Project Cost   ..................................................................................................

$2,000,000

   
   
   

    DTE Energy St. Clair Power Plant Boiler Coal Feeder

Sidock's scope of services included structural engineering for the installation of 5 new boiler feeders and feeder supports and a new mezzanine for mechanical equipment.  Our scope also included mechanical engineering for equipment layout & installation and utility (air & water) installation.
   
Project Cost   ..................................................................................................

$1,000,000

   
   
   

    DTE Energy Monroe Power Plant U2A Winterization Project

Due to new federal regulations, DTE is required to run the Selective Catalytic Reduction System (SCR) year round as opposed to in the summer only.  This change requires complete winterization of a system designed to run in warm months only.  The project consists of constructing a 30,000 sq. ft., 50 ft. tall process building around the existing Urea to Ammonia System (U2A) as well as numerous upgrades to the entire system including heat trace, new controls and programming, emergency ammonia ventilation system, site revisions, etc.  The project also includes structural enclosure of the SCR snow decks which are approximately 80' up on the SCR reactor towers.
   
Project Cost   ..................................................................................................

$5,000,000

   
   
   

 

    DTE Energy River Rouge Power Plant Nitrogen Supply to PCI

The PCI project required a significant increase in nitrogen supply to the Power House Area and to Zug Island, where the flow rate is beyond the capacity of the existing 4" line.  In order to correct this problem Sidock designed a 2nd 4" nitrogen supply line from the Praxair delivery point to the (CPI) area.  The new line required a pressure regulating station located in the vicinity of the (CPI) area and the station consisted of 2 self contained pressure regulators installed in series with a pressure relief valve installed downstream of the regulators.
   
Project Cost   ..................................................................................................

Not Available

   
   
   

 

    DTE Energy Greenwood Energy Center Pipe Stress & Support Analysis

Evaluation and redesign of various boiler house steam piping systems for pipe stress and supports.  Sidock's scope included the initial evaluation studies consisting of as-built verification and pipe stress analysis.  The process was done using Caesar II software and subsequent detail of potential piping re-routes and enhanced support systems.  Examples:  GRNEC Main Steam Low Point Drains, GRNEC Main Steam Turbine Drains, GRNEC Main Steam to Seal Steam, GRNEC Auxiliary Steam Supports, GRNEC Boiler Drain Supports, GRNEC South Attemperation Station Support.
   
Project Cost   ..................................................................................................

Not Available

   
   
   

 

    DTE Energy St. Clair Power Plant Re-Heater Dryer System

Installation of an air purge system to remove stagnant oxygen-saturated water formed during unit shutdown.  Intent is to extend the life of the Unit #1-4 Furnaces horizontal reheated tube banks by eliminating oxygen pitting related corrosion.  Using soot blower air for supply, the air sweep drying systems was piped from a new central air dryer through a common header with isolatable supply branches to Unit #1-4.  Sidock's scope included both mechanical & electrical engineering, feasibility study, equipment specification, and development of piping & electrical installation drawings.
   
Project Cost   ..................................................................................................

Not Available

   
   
   

 

    DTE Energy Trenton Channel Power Plant Coal Re-Claim Tunnel Piping

Installation of new coal feeders in the coal reclaim tunnel conveyors required that various utilities be rerouted.  Sidock's scope included development of new drawings showing fire protection and steam & wash down water reroutes as well as removal of abandoned steam and condensate piping.
   
Project Cost   ..................................................................................................

Not Available

         

site info

 
   